{"id":9569,"date":"2024-09-25T11:01:22","date_gmt":"2024-09-25T11:01:22","guid":{"rendered":"https:\/\/acjce.com\/?page_id=9569"},"modified":"2024-09-25T11:03:39","modified_gmt":"2024-09-25T11:03:39","slug":"messing-up-decarbonization-2","status":"publish","type":"page","link":"https:\/\/acjce.com\/?page_id=9569","title":{"rendered":"Coal returns to the CPEC"},"content":{"rendered":"\n<p>News that the Pakistan government plans to secure financing and start construction on a long-stalled <a href=\"https:\/\/cpec.gov.pk\/project-details\/5\">300 megawatt coal-fired power plant<\/a> in the port city of Gwadar has triggered a debate on the direction of the country\u2019s energy sector. Set to be built and funded by Chinese state-owned entities, recent developments have also raised fresh questions about China\u2019s <a href=\"https:\/\/www.thethirdpole.net\/en\/energy\/china-to-stop-building-new-coal-power-projects-overseas\/\">pledge<\/a> \u2013 made at the UN General Assembly in 2021 \u2013 not to build any new coal power plants overseas.<\/p>\n\n\n\n<p>The Gwadar coal power plant was first conceived in 2016, with an estimated cost of <a href=\"https:\/\/cpec.gov.pk\/project-details\/5\">USD 542.32 million<\/a>. It is to be constructed by the Chinese company CIHC Pak Power, a subsidiary of the state-owned China Communications and Construction Group. The plant was recently <a href=\"https:\/\/www.brecorder.com\/news\/40221115\">reported<\/a> to have secured financing from the Industrial and Commercial Bank of China (ICBC), China\u2019s largest commercial bank. Once completed, it is intended to supply power, on a priority basis, to the industries being set up at the Gwadar Free Zone (GFZ), a special economic zone at Gwadar port that forms part of the <a href=\"https:\/\/www.thethirdpole.net\/en\/tag\/cpec\/\">China-Pakistan Economic Corridor<\/a> (CPEC), the USD 62 billion bilateral infrastructure and connectivity project between China and Pakistan.<\/p>\n\n\n\n<p>The environmental impacts of coal power \u2013 from local air and water pollution to carbon emissions \u2013 have made the project controversial.<\/p>\n\n\n\n<p>\u201cWe are pushing the Chinese company to complete its financial closure by&nbsp;31 December 2023, and start construction at the earliest so that it can be completed by 2025,\u201d Shah Jahan Mirza, managing director of the Pakistan government-owned <a href=\"https:\/\/www.ppib.gov.pk\/\">Private Power and Infrastructure Board<\/a> told The Third Pole. \u201cElectricity shortage is the biggest impediment to developing Gwadar,\u201d he said.<\/p>\n\n\n\n<p>Pakistan\u2019s energy sector is dominated by fossil fuels. According to the country\u2019s <a href=\"https:\/\/www.finance.gov.pk\/survey\/chapter_22\/PES14-ENERGY.pdf\">Finance Division<\/a>, as of April 2022, just under 60% of total installed generation capacity used fossil fuels, including gas, oil and coal. Just 3% of generated electricity in the 2022 fiscal year came from non-hydropower renewables. Pakistan\u2019s <a href=\"https:\/\/unfccc.int\/sites\/default\/files\/NDC\/2022-06\/Pakistan%20Updated%20NDC%202021.pdf\">Nationally Determined Contribution<\/a> (NDC) \u00ad\u2013 its climate pledge under the Paris Agreement \u2013 targets 60% renewable energy generation by 2030, including hydropower. The NDC also states: \u201cFrom 2020, new coal power plants are subject to a moratorium.\u201d<\/p>\n\n\n\n<h4 class=\"wp-block-heading\" id=\"h-no-new-chinese-backed-coal-power-overseas\">No new Chinese-backed coal power overseas?<\/h4>\n\n\n\n<p>In 2021, China\u2019s president Xi Jinping <a href=\"https:\/\/www.fmprc.gov.cn\/eng\/topics_665678\/kjgzbdfyyq\/202109\/t20210923_9591806.html\">announced<\/a> that China would not build any new coal-fired power projects abroad. He also stated that the country would increase support for low-carbon energy in developing countries.<\/p>\n\n\n\n<p>Bao Zhong, political counsellor at the Embassy of the People\u2019s Republic of China in Islamabad, told The Third Pole that the Chinese government stands by the pledge. \u201cThe Gwadar coal-fired plant is not a new project and has been in the CPEC framework since 2016,\u201d she said. \u201cWe hope the Gwadar power plant\u2019s construction begins as early as possible to ease the power shortage there.\u201d<\/p>\n\n\n\n<p>Ahsan Iqbal, Pakistan\u2019s federal minister for planning, development and special initiatives, seconded Bao\u2019s comments. \u201cThis project was approved in 2017, long before the Chinese president\u2019s proclamation.\u201d<\/p>\n\n\n\n<p>In April 2022, China\u2019s National Development and Reform Commission (NDRC), the country\u2019s top economic planning and management body, released an <a href=\"https:\/\/www.ndrc.gov.cn\/xxgk\/zcfb\/tz\/202203\/t20220328_1320629.html?code=&amp;state=123\">interpretation<\/a> of the 2021 pledge, clarifying a moratorium on all \u201cnew build\u201d projects. It also stated that projects already under construction should proceed \u201csteadily and cautiously\u201d. Some commentators <a href=\"https:\/\/www.thethirdpole.net\/en\/energy\/chinas-no-overseas-coal-pledge-15-projects-cancelled-grey-areas-remain\/\">suggested<\/a> that the wording also left the door open to renegotiating contracts and pursuing alternatives to coal, such as gas, solar and wind power projects.<\/p>\n\n\n\n<p>Azhar Lashari from the Policy Research Institute for Equitable Development (PRIED) believes that China\u2019s continued support for the Gwadar coal power plant violates the April 2022 NDRC interpretation as \u201cno civil works on the plant had started.\u201d<\/p>\n\n\n\n<p>Speaking with The Third Pole, Lashari said the support is \u201cnot only a violation of [China\u2019s] pledge to not build any overseas coal power plants, but it has undermined the battle against global warming and climate change\u201d.<\/p>\n\n\n\n<p>While construction of the Gwadar plant has not yet commenced, Bao of the Chinese Embassy in Islamabad said: \u201cThe preparation for construction of the power plant is almost ready and it would be unfortunate if hurdles come in its way.\u201d<\/p>\n\n\n\n<p>According to Mirza, the delay in starting construction was due to \u201cproblems in <a href=\"https:\/\/profit.pakistantoday.com.pk\/2019\/11\/04\/300mw-power-project-finally-inaugurated-in-gwadar\/\">land acquisition<\/a> and <a href=\"https:\/\/archive.pakistantoday.com.pk\/2018\/02\/28\/balochistan-concerned-over-harmful-aspects-of-coal-power-plants\/\">environmental approvals<\/a> by the Balochistan government as well as lenders and Chinese state-funded&nbsp;insurance company <a href=\"https:\/\/www.sinosure.com.cn\/en\/Sinosure\/Profile\/index.shtml\">Sinosure<\/a> approvals\u201d. Although the tariff&nbsp;(the rate at which the Chinese company will sell electricity)&nbsp;had been determined in 2019, the land acquisition for the plant did not happen until 2020 and the power purchase agreement&nbsp;between the Chinese company and GFZ&nbsp;was signed in early 2021.<\/p>\n\n\n\n<p>The Pakistan government had <a href=\"https:\/\/www.brecorder.com\/news\/40227743\">attempted<\/a> to persuade Chinese partners to shift the project to Thar, a district of Pakistan\u2019s Sindh Province which is rich in lignite coal reserves, in order to use domestic coal and so save on precious foreign exchange. <a href=\"https:\/\/cpec.gov.pk\/project-details\/4\">Block II<\/a> of the Thar coal mine is a CPEC project.<\/p>\n\n\n\n<p>\u201cShifting the plant to Thar would mean including this as a new coal project and China has taken a principled stand not to support new coal projects,\u201d Bao told The Third Pole. She added that China was well aware of environmental issues around coal. \u201cWe have scrutinised the plant from every angle, including the environmental one, and tried to look at alternatives. Coal is the only feasible fuel. We want to help Pakistan develop Gwadar, and bring in investment; the only way to be able to attract investors is to give it sustainable power,\u201d she said.<\/p>\n\n\n\n<h4 class=\"wp-block-heading\" id=\"h-solar-versus-coal-in-gwadar\">Solar versus coal in Gwadar<\/h4>\n\n\n\n<p>Questions have also been raised around how the Gwadar coal power plant fits into the Pakistan government\u2019s long term energy policies. In 2020, Pakistan\u2019s former prime minister Imran Khan <a href=\"https:\/\/www.climateambitionsummit2020.org\/ondemand.php\">announced<\/a> to the world at the <a href=\"https:\/\/www.climateambitionsummit2020.org\/\">Climate Ambition Summit<\/a> that Pakistan had \u201cdecided that we will not have any more power based on coal\u201d, and that two power projects approved under CPEC that were to use imported coal \u2013 at Muzaffargarh and Rahim Yar Khan \u2013 had been scrapped. He also said that with regards to indigenous coal, Pakistan would focus on producing energy through coal liquefaction or gasification, \u201cso that we do not have to burn coal to produce energy.\u201d<\/p>\n\n\n\n<p><strong>Refrence Link<\/strong><\/p>\n\n\n\n<p>https:\/\/www.thethirdpole.net\/en\/energy\/gwadar-coal-returns-to-china-pakistan-economic-corridor\/&nbsp;<a href=\"https:\/\/www.thethirdpole.net\/en\/energy\/gwadar-coal-returns-to-china-pakistan-economic-corridor\/\" target=\"_blank\" rel=\"noreferrer noopener\">https:\/\/www.thethirdpole.net\/en\/energy\/gwadar-coal-returns-to-china-pakistan-economic-corridor\/<\/a><\/p>\n\n\n\n<p><strong>Published Link<\/strong><\/p>\n\n\n\n<p>The Third Pole&nbsp;<a href=\"https:\/\/www.thethirdpole.net\/en\/energy\/gwadar-coal-returns-to-china-pakistan-economic-corridor\/\" target=\"_blank\" rel=\"noreferrer noopener\">https:\/\/www.thethirdpole.net\/en\/energy\/gwadar-coal-returns-to-china-pakistan-economic-corridor\/<\/a><\/p>\n\n\n\n<p><\/p>\n\n\n\n<p><\/p>\n\n\n\n<p><\/p>\n\n\n\n<p><\/p>\n","protected":false},"excerpt":{"rendered":"<div class=\"tmnf_excerpt\"><div class=\"tmnf_excerpt\"><p>News that the Pakistan government plans to secure financing and start construction on a long-stalled 300 megawatt coal-fired power plant in the port city of Gwadar has triggered a debate on the direction of the country\u2019s energy sector. Set to be built and funded by Chinese state-owned entities, recent developments have also raised fresh questions &hellip;<\/p>\n<\/div><\/div>","protected":false},"author":1,"featured_media":0,"parent":0,"menu_order":0,"comment_status":"closed","ping_status":"closed","template":"template-fullwidth.php","meta":{"_acf_changed":false,"footnotes":""},"class_list":["post-9569","page","type-page","status-publish","hentry"],"acf":[],"_links":{"self":[{"href":"https:\/\/acjce.com\/index.php?rest_route=\/wp\/v2\/pages\/9569","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/acjce.com\/index.php?rest_route=\/wp\/v2\/pages"}],"about":[{"href":"https:\/\/acjce.com\/index.php?rest_route=\/wp\/v2\/types\/page"}],"author":[{"embeddable":true,"href":"https:\/\/acjce.com\/index.php?rest_route=\/wp\/v2\/users\/1"}],"replies":[{"embeddable":true,"href":"https:\/\/acjce.com\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=9569"}],"version-history":[{"count":2,"href":"https:\/\/acjce.com\/index.php?rest_route=\/wp\/v2\/pages\/9569\/revisions"}],"predecessor-version":[{"id":9572,"href":"https:\/\/acjce.com\/index.php?rest_route=\/wp\/v2\/pages\/9569\/revisions\/9572"}],"wp:attachment":[{"href":"https:\/\/acjce.com\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=9569"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}